Construction Activities and Infrastructure Investments
Each week, we'll update this page with the latest information on construction activity. You'll find updates for city projects, plats and site developments. Check back each week for updates or follow us on Facebook.
Si necesita esta informaciĂłn traducida al español, comunĂquese con nuestra oficina al (616)530-7260.
City Projects
Week of May 26, 2025
CITY OF WYOMING PROJECTS​
Division Avenue Watermain – 36th St to 44th St (including work on Maplelawn) (Dykema Excavating)
Pavement has been removed on Division Avenue from 44th Street to Bellevue Street. Street is open to local businesses, but closed to through traffic. The best way to access businesses is from side streets. Contractor has completed watermain installation in phase 1 (44th Street to Bellevue Street) and testing is in progress. The contractor is working on watermain installation on Maplelawn and expects to be ready for testing by the end of the week.
Wyoming City Center Bridge Project (Anlaan Construction)
The contractor is working on the pedestrian bridge over 28th Street. Installation of architectural panels is planned to start next week. Periodic Lane closures are planned on 28th Street.
Wyoming City Center Trail Project (Katerberg-Verhage and Strain Electric)
Trail work continues in Pinery Park. HAWK signal work will continue in late summer when strain poles are available.
PRIVATE DEVELOPMENT PROJECTS
Benteler Automotive Fireline (4011 Stafford Ave., SW) – Dan Hoe Excavating
Watermain installation and testing are complete. Utility work continues in 40th Street, which will require periodic closures of 40th Street.
Corewell Health Watermain & Fireline (300 – 36th St., SW) – Connan Inc.
Watermain and Firelines are complete. Right Turn lane and traffic signal on 36th Street scheduled later this spring.
Godwin Mercado (36th St. Market) Watermain – GVL Excavating
Remaining drive approach on 36th Street is planned in the next couple weeks.
Holtwood Street (old GM Plant off Buchanan Ave) – Dan Hoe Excavating
Contractor is working on storm sewer with road construction to follow. Storm sewer work has been slowed due to utility conflict. Entrance on Buchanan is planned to start in a couple weeks and will require a lane closure.
Malta Woods (N. off 56th, E of Wilson) – Fischer Idema
Contractor completed installation of waterservices. Contractor is starting on storm sewer and plans to connect storm sewer in 56th Street in a couple of weeks.
Rivertown Valley Phase 7 (Reserve Drive/Nile Drive area) – Schippers Excavating
Watermain tie-in is planned for this week with waterservices to follow. Contractor is working on storm laterals and grading for the street.
Courtyard at Wyoming (4051 Del Mar Drive) – Excel Excavating
Watermain and Sanitary Sewer construction is expected to start in approximately 2 weeks. This work will require lane closures on Del Mar Drive.